With LIV Golf infrastructure works well underway, we would like to provide members with a progress update on the build.

Works underway or completed

  • Construction works are virtually complete on “The Watering Hole” (or 12W)
  • Construction works are virtually complete on the Club 54 & Chalets build around the 18W green
  • Construction works are virtually complete on Barossa hospitality area adjacent 14W, 15W & 16W
  • As of 7th April, 17 of 22 camera towers builds were complete or underway, and 10 of 20 superscreen builds were underway
  • All 10 corporate hospitality builds are in progress
  • Construction works on 5 of 12 viewing decks are underway
  • The Flight Deck infrastructure build on the driving range commenced on Tuesday, 9th April
  • The Media Centre and broadcast compound builds commenced on 2nd April
  • Fan Village infrastructure works on 1st and 2nd West underway

Works coming up

  • Viewing decks on the 1st East tee and putting green commence shortly
  • The C-Suites infrastructure build on the Pro Shop terrace commences on Wednesday, 10th April