With LIV Golf less than two weeks away, we would like to provide members with a progress update on the build.

Works underway or completed

  • LIV Golf media call held on Tuesday, 9th April
  • Construction works are virtually complete on all hospitality areas with handover to trades for fit out underway
  • Concert stage construction works underway in Fan Village on 1st West fairway
  • Flight Deck construction works underway on driving range
  • Viewing platforms on 10th East tee (1st LIV) almost complete
  • LED Ribbon screens installed at Watering Hole
  • Completion of all scaffold camera towers (22 of 22) and superscreen structures (20 of 20)
  • Player scaffold bridge over pedestrian walkway almost complete
  • C-Suite construction works underway on Pro Shop terrace

Upcoming works

  • Transition from construction site to event site
  • Fit out of all hospitality areas
  • Installation of food & beverage facilities, signage, roping, fencing, etc.
  • Handover of site to LIV Golf