Following the rain event we encountered on the 28th February 2022 which flooded the gym and locker rooms, the remaining work has now been approved and scheduled to be completed.

Plastering and painting of the Gym/Physio corridor was completed in October 2022, however part of the flooring in the Gym and the entire carpet in the Men’s Locker Room will be replaced in the coming weeks.

Works to repair the Gym flooring and carpet tiles in the men’s locker rooms will take place in two stages with the northern entrance closed one day and the southern entrance the following week with the dates as follows:

  • Monday 23rd January – Gym flooring repairs and commence first half of the repairs in the Men’s Locker Room
  • Tuesday 24th January – Complete first half repairs of Men’s Locker Room
  • Monday 30th January – Complete second half repairs of Men’s Locker Rooms

The Locker Rooms will still be available during this time but only via one entrance.

We thank members for their understanding and patience during this time and apologise in advance for any inconvenience.